- Date: March 2011Company: LGH / Santiago – Metropolitan Region.Installation and mounting of the metering outfit:- Verification of service voltages and the sequence of phase.- The distribution local company collaborates to disconnect the junction of the supplying network of medium voltage.- Verification that there is no voltage in both, high and low voltage.- Installation of grounding protection.
– The electricity local company is present when the metering outfit is removed.
– Installation of metering outfit. It is not integral but according to the mechanical mounting and medium voltage connection.
– Removal of grounding protection.
– The staff of the electricity local company is in charge of the energization of the medium voltage network.
– Verification of the service voltages and the sequence of phase.
.