Date: September 2009

Company: ET / RANCAGUA – VI Region

Some tests were realized to launch the distribution transformer:

– Visual inspection of transformer.

– Measurement of the reason of transformation in all taps.

– Measurement of resistance of medium voltage coils in all taps.

– Measurement of resistance of low voltage coils.

– Measurement of resistance of insulation: High voltage- Low voltage. High Voltage. Mass. Low Voltage- Mass.